LGOIMA: Dixon Street upgrade
The Dixon Street upgrades have gone quiet. I requested official information about why.
The question
In 2025, Wellington City Council ran drop-in sessions on a redesign of Dixon Street, with outdoor dining, more space for people, and a bike connection between Taranaki and Willis streets. Since then, we haven’t heard a peep.
The Council had approved about $800,000 for design and a business case in May 2025, with a construction budget of around $7 million. I asked what happened after the engagement: the feedback, the current design, the business case, the spend to date, and any advice about pausing or rescoping the project.
Read the full response:
A. The design engagement and what it found
The dates, channels and materials of all engagement since 2025; all feedback received; any engagement report or "what we heard" document; and a list of design changes made in response.
Informal consultation with key stakeholders was undertaken on 1 September 2025 and 4 November 2025, please see appendix one for a copy of the drop in letter and supporting material provided at the meetings. Feedback from these drop-in sessions will inform the business case, which will be made publicly available when the paper goes to committee.
You have asked for engagement reports/ and design changes made for the Dixon Street project. This type of engagement/reporting does not take place so early in a project. Once the business case has been presented to the Council and formal consultation takes place, the project team will then share the findings of the engagement and be able to present any design changes in response to the engagement. This part of your request has been refused under section 17(e) that the alleged document to contain the information requested does not exist. The project is Planned to be considered as part of the 2027 Long-term Plan process. The timing of when or if this piece of work will take place is still to be confirmed.
B. The current design and business case
The most recent design drawings and reports from WSP or others, the business case funded by the 8 May 2025 committee decision, and any options assessment.
In May 2025, the Planning and Environment Committee instructed officers to bring a Business Case to the Committee in early 2026 for consideration. Following the Triennium Plan decision to separate the Te Aro Park and Dixon Street projects, a revised Business Case for the Te Aro Park Upgrade has been completed in draft form. The draft assesses options, and associated risks, that could be delivered within the approved budget as well as under an extended scope, and it is planned to be considered as part of the 2027 Long-term Plan (LTP) process, where the information will be made available to the public for consultation.
As the Business Case remains in draft and is intended to be presented to the Council for public consultation, we have refused this part of your request under section 7(f)(i) of the LGOIMA, to maintain the effective conduct of public affairs through the free and frank expression of opinions by, between, or to members, officers, or employees of a local authority in the course of their duties.
C. Cost and spend
The current cost estimate and any quantified risk assessment; spend to date against the ~$800,000 design and business-case budget, including amounts invoiced by WSP.
Please see page 3 of the Question and Answer for the City Strategy and Delivery committee 2026-08-06-QA-CSD.
Expenditure to date is $2.46m. This is made up of:
- Pōneke Promise Stage 1 (Dixon St temporary changes made in 2022) cost:
- $570k (OPEX) – Plants and monitoring and evaluation
- $0.714 (CAPEX) - design, consultants, engagement, investigations, project management and physical works. - A reporting error has been identified. The report shows $1.14m (CAPEX), instead of $0.714m for stage 1.
- Pōneke Promise Stage 2 has to date cost:
- $1.176 million spread across the following budgets - Pōneke Promise: $0.604m (CAPEX), Central City Upgrades (Dixon St): $0.522m (CAPEX), Community Services Safety Te Aro Park: $50k (CAPEX). This includes design, consultants, engagement, investigations and project management to date.
D. Programme, governance and status
The current programme; all briefings to the Chief Executive, Mayor's office, councillors or committees since 1 May 2025; any advice about pausing, rescoping or delaying the project; and all correspondence with NZTA about funding.
As the project is on hold the Council has not received any direction to date on progressing this work. […] There is no budget decision on the Dixon Street upgrades in the Triennium Plan other than partnerships with Mana Whenua. There are no links to the Golden Mile Independent Revalue Review or the Courtenay Place programme.
The Council summarised two briefings:
- Ward councillors, 4 December 2025: general updates, strategic alignment of Te Aro Park and Dixon Street, the historical decision timeline, the values, brief and objectives for the project, and renders.
- Executive Leadership Team, 16 October 2025: general updates; a pathway for the business case to Council in February 2026 ("critical decisions"); ELT to socialise the project with Mayor Little; wider stakeholder communication; and construction interfaces with Golden Mile Stage 1, including the "risk of Golden Mile Stage 1 not progressing leading to gap in primary cycle route".
There has been no communication with NZ Transport Agency since 2024 regarding funding or co-funding for the Dixon Street Upgrades. This part of your request has been refused under section 17(e) of the LGOIMA that the document alleged to contain the information requested does not exist, or despite reasonable efforts to locate it, cannot be found.
Appendix one: drop-in materials
The appendix has the drop-in invitation letter and four boards: plan drawings for Section B (Victoria to Cuba) and Section C (Cuba to Taranaki), a project timeline, a project background panel, and cross-sections showing footpath, outdoor dining, cycleway and parking for Willis to Cuba and a shared zone for Cuba to Taranaki.
a lil description so people can find it
In a LGOIMA response dated 20 August 2026 (ref 26-0623), Wellington City Council said the Dixon Street upgrade in Te Aro is on hold and will be considered through the 2027 Long-term Plan, with no confirmed timing. The Council refused to release the draft business case under section 7(f)(i), said no engagement report or record of design changes exists, and summarised briefings to ward councillors (December 2025) and the Executive Leadership Team (October 2025). It released the letter and design boards from stakeholder drop-in sessions held on 1 September and 4 November 2025, showing proposals for outdoor dining, wider footpaths, a bike connection between Taranaki and Willis streets, and a shared zone between Cuba Street and Te Aro Park.